Excavation of Tunnel S2 at the center of construction work
A recent visit to the construction site near the settlement of Viniani coincided with excavation of Tunnel S2. The tunnel is 2,480 meters long and is one of the technically challenging parts of the project, which includes two tunnels. The site inspection was attended by Minister of Infrastructure and Transport Christos Dimas.
Completion of the road and its opening to traffic are expected in late 2028. Konstantinos Mitzalis, CEO of the AVAX Group, said construction is progressing in line with the approved schedule.
A connection from Lamia to Antirrio
The Bralos–Amfissa axis is part of the Lamia–Itea–Antirrio route. Once completed, the route will connect the PATHE motorway with the Ionian Motorway, strengthening the road link between Central and Western Greece. The project is particularly significant for the regions of Phthiotis, Phocis and Aetolia-Acarnania.
The project forms part of the E65 trans-European road network and extends for a total of 30.7 kilometers. The anticipated change to the area’s road network is linked to the creation of a continuous route between major road axes, not merely to the construction of a standalone section.
“Work on this complex project is continuing within the approved schedule.”
Konstantinos Mitzalis, CEO of the AVAX Group
Bridges, interchanges and three distinct sections
The main project covers 24 kilometers and includes seven bridges, six at-grade interchanges and two twin, one-way tunnels. The tunnels are 2,150 and approximately 2,480 meters long, with two traffic lanes in each bore.
The overall route also includes the 2-kilometer Gravia bypass, which has already been built. The 4.7-kilometer intermediate section, from the end of the bypass to the Bauxite Mines at-grade interchange, is being carried out under a separate contract. This structure explains why the overall road axis comprises individual sections with different scopes.
European co-financing and the next milestone
Funding is secured through the “Transport 2021–2027” program, co-financed by the European Regional Development Fund. The next milestone for the project is the continuation of construction work according to the approved schedule and, ultimately, the opening of the road axis to traffic in late 2028.
The schedule and completion of the individual sections are especially important to the operation of the overall connection. The available information gives no alternative opening date and does not specify a date for the next construction milestone.
The Greek dimension
The project concerns road links between areas of Central and Western Greece, particularly the regions of Phthiotis, Phocis and Aetolia-Acarnania.